The BIM process for the shell and core began in April 2015 and is very close to being complete with only the roof plant levels to be issued for construction. The BIM process for the CAT A and CAT B offices areas is programmed to commence in September 2016 and be complete by March 2017. Overall the project has run very smoothly and this has been greatly down to the close working relationship with Skanska, the design team and all trade contractors. There has been the odd bump along the way, but by having the collaborative expertise all issues have quickly and painlessly been resolved during the BIM process.